Fire and resilience

The Private Finance Initiative - A Guide for Authorities (continued...)

(Continued...)

The procurement process

PFI procurement is a negotiated process. It normally takes between 18 and 24 months from advertisement to contract award. Typical PFI procurements will go through the following processes:

Planning

  • Establish business need
  • Decide whether the project is suitable for PFI
  • Respond to ODPM request for Bids to go on the FRS PFI Programme
  • Decide whether the project is affordable and likely to provide value for money

Outline business case

  • Submit an Expression of Interest document to ODPM
  • If successful, develop an Outline Business Case (OBC)
  • Test market interest
  • Submit OBC to ODPM for Ministerial approval and PRG endorsement
  • Obtain approval to proceed

Advertising

  • Advertise in the Official Journal of the European Union OJEU

Qualification of bidders

  • Send out pre-qualification questionnaire to companies that respond to OJEU advert
  • Evaluate responses
  • Draw up a short list of bidders
  • Send out Invitation to Negotiate (ITN) to shortlisted firms
  • Clarification meetings with bidders

Evaluation of bids

  • Receive and evaluate bids for compliance with financial, technical and legal criteria, affordability and value for money

Tendering and negotiations

  • Select preferred bidder
  • Negotiate with the preferred bidder on issues raised by their proposals, for example, negotiations around the project costs and the accountability and pricing of risk

Best and final offer

  • Invite Best and Final Offer

Final business case

  • Submit Final Business Case to ODPM
  • Ensure the project is still affordable, compatible with the SoPC etc

Contract

  • Contractual close
  • Financial close

Service commencement

  • Mobilisation. There will normally be a 12 - 24 month period whilst new facilities are created
  • Commencement of service provision

The above may vary from procurement to procurement, for instance the FRA may issue selected bidders with an Invitation to Submit Outline Proposals (ISOP) before issuing an ITN. This enables the authority to gain an insight into what the bidders might offer. Again, it may be felt to be unnecessary to ask the preferred bidder to provide a Best and Final Offer (BAFO) as nothing much has changed from the ITN bid submission.

What does a PFI contract contain?

Fire and Rescue Service marked carThe contract document - known as the Project Agreement - will consist of three main parts; the output specification, the payment mechanism and the contract terms.

The Output Specification - This sets out what is expected of the SPV. It is written in terms of outputs or outcomes. This means specifying what the authority expect to see as the result of this project rather than how it expects that result to be achieved. This allows the PSP to bring innovative ways of thinking and working into the project.

Payment Mechanism- This has two main elements to it: Availability Standards and Performance Standards.

Availability Standards - these define when the asset is considered 'available for use'.

Performance Standards - these relate to any standards not covered by the Availability Standards, in general the service and maintenance standards.

Contract terms - This contains the legal framework for the contract drawn up between the SPV and the FRA. HM Treasury issue guidance and model contract conditions which must be adhered to in drafting PFI contracts.

How does the department decide what projects should be taken forward?

ODPM will issue criteria when bids are invited to go on the FRS PFI programme. In addition all local authority projects are reviewed by the Project Review Group (PRG) at the OBC stage. The PRG also have criteria which need to be met based around bankability, affordability and risk allocation. ODPM will compare different bids from various Fire Authorities against the criteria, some of which will be linked to the modernisation of the Fire and Rescue Service. In addition ODPM will need to take account of the number of PFI credits available to support schemes.

In addition authorities are required to look at the most economic, effective and efficient means of service delivery as part of a Best Value review and PFI is just one approach to procuring services. Authorities bids should therefore explain why PFI funding provides the best value option, for funding this project and the other options considered. It is recommended that Authorities use Treasury's Value for Money guidance, which can be found on their website www.hm-treasury.gov.uk

How is the service paid for?

The FRA will pay a yearly 'unitary charge' to the SPV. The charge will be based on the availability and performance of the facilities and associated services, and deductions will be made for non-availability or poor performance.

  • Availability relates mainly to the physical condition of the assets. Availability standards are defined at the beginning of the PFI process. An example of this could be that the building 'should be watertight at all times'. This might mean that a fire station with a leaking roof did not meet the availability standard and was therefore 'unavailable'. If the asset or assets do not meet these standards then the SPV forfeits an element of the Unitary Charge relating to the asset or assets until the standards are met.
  • Performance relates to how well the SPV carries out the services it is responsible for. A performance standard could be, '98% of requests for emergency repairs to equipment must be answered in 12 hours to receive full payment'. If the SPV only answers 96% of the emergency requests within 12 hours during a given time period then a certain percentage of its payment for that month would be deducted. There is usually a mechanism to increase the penalties if the standards continue to be below the requirement.

The payment mechanism will be structured to ensure value for money by reflecting the allocation of risks, and will be based on agreed standards and deductions.

Allocation of risks

A fire engineAll projects involve risk. It is the allocation of risks to the party best able to manage them, which allows innovative solutions in PFI deals and helps deliver value for money.

The PSP will be asked to be responsible for those risks that they are best placed to manage. They will not, for example, be asked to decide how many fire stations are needed - this is a decision for the FRA, but they will be responsible for ensuring that the agreed number are available to the required condition when needed.
 
At an early stage in the procurement the SPV will be provided with an indication of the likely risks and asked to confirm their willingness to accept significant risk transfer. Negotiations will normally focus on whether the proposed allocation of risks produces the best value.

Who monitors the contract?

The Fire Authority and the SPV will both need to monitor the level of service performance. Exactly who does what needs to be made completely clear from the outset and laid down in the contract details, including how any disputes should be dealt with.

What happens at the end of the contract term?

It all depends on the particular circumstances but the options will be contained in the contract. The FRA might have the right to acquire the building at a specified value or to walk away if it has no further need for it.

Alternatively there might be provision to re-tender the service with the building being made available to the successful bidder. Whether the SPV get paid for the asset will depend on the approach to residual value and whether this is reflected in the charges. But the contract will ensure that the asset is maintained to the required standard and is capable of continued use if required.

Further information and glossary of terms

Questions about the use of PFI in the Fire and Rescue Services should be directed to:

David Green & Kate Hepher who are responsible for PFI projects for the Fire and Rescue Authorities at ODPM.

Fire Service Improvement Team
Office of the Deputy Prime Minister
17B Portland House
Stag Place
Victoria, London
SW1 E5LP
Tel: 0207 944 4523

The Private Finance Unit at HM Treasury is responsible for Government policy on PFI/PPP and can supply information on the subject. Contact details are:

Private Finance Unit
HM Treasury
1 Horse Guards Rd
London SW1A 2HQ
Tel: 020 7270 4558
www.hm-treasury.gov.uk

For general guidance on PFI in local authorities, contact:

4ps (Public, Private Partnerships Programme)
South Entrance
7th Floor
Artillery House
Artillery Row
London SW1P 1RT
Tel: 020 7808 1470
www.4ps.gov.uk

Glossary of Terms

BAFO - Best and Final Offer

FRA - Fire and Rescue Authorities

ISOP - Invitation to Submit Outline Proposals

ITN - Invitation to Negotiate

OBC - Outline Business Case

ODPM - Office of the Deputy Prime Minister

PFI - Private Finance Initiative is a procurement mechanism by which the public sector contracts to purchase quality services on a long term basis from the private sector so as to take advantage of private sector management skills.

PPP - Public Private Partnerships bring public and private sectors together in long term partnership for mutual benefit. The PPP label covers a wide range of different types of partnership including the Private Finance Initiative, the introduction of private sector ownership into state-owned businesses and selling Government services into wider markets.

PRG - Project Review Group.

PSP - Private Sector Partner.

RSG - Revenue Support Grant.

SPV - Special Purpose Vehicle. This is a group of companies that have joined together to form a single organisation for the purposes of bidding for a PFI contract.

Value for money - The Government's procurement policy is that all public procurement of goods and services, including works, is to be based on best value for money - the optimum combination of whole life cost and quality to meet the requirement.

You may also be interested in …

On this site

My favourites